12th Street Court – Tuesday, July 31, 2012

July 31, 2012  |  By pswrealestate

Site work continues.  Trenching for stormwater collection system is ongoing. We should wrap up storm water this week.  

Read More

Forest Trail – Wednesday, July 25, 2012

July 25, 2012  |  By pswrealestate

Some interior shots of the soon-to-be finished products…

Read More

Forest Trail – Tuesday, July 24, 2012

July 24, 2012  |  By pswrealestate

Landscaping started this week, and the brick pavers for the main drive are almost complete. We are looking forward to moving our well deserving buyers in next month!  

Read More

August 2012

July 24, 2012  |  By pswrealestate

2                         First Thursday – http://www.firstthursday.info/ 4                         Lake Travis Hot Air Balloon Festival – www.centraltexasballooning.com 5, 12, 29, 26 …

Read More

12th Street Court – Wednesday, July 11, 2012

July 12, 2012  |  By pswrealestate

We have cleared the buildings and demolished all site work and vegetation.  The complex has been staked, and the site grading begins tomorrow.

Read More

Forest Trail – Wednesday, July 11, 2012

July 12, 2012  |  By pswrealestate

Our sleek Forest Trail kitchens are coming together!

Read More

Forest Trail – Tuesday, July 10, 2012

July 10, 2012  |  By pswrealestate

Homes 3 through 10 now have power. Heating and A/C running on most homes as well. Hardwood floors began last week and continues this week.  Sheetrock concluded in lot 11 last week and interior paint and trim work is happening …

Read More