May 13, 2012  |  By pswrealestate

Started trim last week. Continued with Sheetrock install as well as
texturing of the walls. Also, we’ve continued with foundations of 1
and 11, plumbing and electrical in 2 and 7, and concrete stain in lot
6. The rain last week helped test the neighborhood and roofs for proper drainage.